China Railway 25th Bureau Rehearses Hongshui River Bridge Builds in a Digital Twin

A live digital twin of Guangxi's Hongshui River Grand Bridge rehearses lifts and pours in advance and monitors the build.

China
Construction
#DigitalTwin
Added on

Worked on this project?

Get credited on this page

Aerial view of a red steel arch bridge spanning a river between two tall red cable-crane towers, with the arch closed above the river
Arch-rib closure of the Hongshui River Grand Bridge on the Liuzhou–Qinzhou Expressway, the construction whose cable-crane lifts were rehearsed in the project's digital twin.

Sign in to view 2 more media items

China Railway 25th Bureau Group (中铁二十五局) is using a digital twin to plan and control construction of the Hongshui River Grand Bridge, the controlling structure of the Liuzhou–Qinzhou Expressway in Xingbin District, Laibin, Guangxi. The project team rehearses steel-member lifting and over-river pours in the virtual model before doing them on site, and uses the same model to watch the physical build.

How the twin works

According to Guangxi Daily, the project's smart control centre displays a 1:1 digital replica of the bridge that updates in real time. The team built it by combining BIM modelling, aerial imagery of the site and Internet-of-Things sensing, drawing on China Railway Construction Corporation's bridge-building technology.

Project lead 陈永贵 says that arch rib lifting and over-river pouring can all be simulated in advance. During physical construction the system collects data on bridge deformation, structural stress, water level and wind speed, and issues an automatic warning when an indicator goes abnormal.

Progress and reported results

  • Guangxi Daily reports that, relying on the system, steel-member lifting precision on the bridge has been held to millimetre level; no measurement method or baseline is given.
  • A June 2025 report from 铁建投资, which leads investment in the expressway, said the team was already using the digital twin to simulate arch rib lifting when the bridge's arch ribs were closed.
  • On 20 November 2026 the last beam was set and the bridge achieved full through-connection, moving the project into its final construction phase.
  • The expressway is expected to open to traffic at the end of June 2027.

Quotes

“We can simulate the arch rib lifting and the over-river pouring in full, in advance.”

Project Summary

This information is available to registered members of XRHQ. Sign up for free below.

Experience

Available to XRHQ members

Sources

Available to XRHQ members

Know more about this project? Help us fill in any missing details.

Edit this project →

Worked on this project?

Get credited on this page

This write-up is free to reuse with credit — CC BY 4.0.