Sarawak public works halves design time on a cross-state road with a 3D digital twin

Drone-captured 3D models, 4D construction sequencing and a shared web viewer coordinate a 335 km road across Borneo's mountainous interior.

#DigitalTwin

Dave

Added on
Were you involved in this project?
Aerial view of a winding dirt road cut through dense, green forested hills in northern Sarawak, East Malaysia, on the Sarawak Sabah Link Road Phase 2 alignment.
Photo: JKR Sarawak

Sign in to view 2 more media items

Data Points (8)

This information is available to registered members of XRHQ. Sign up for free below.

and 2 more — sign up to view

Background

The Sarawak Sabah Link Road Phase 2 (SSLR2) is the first continuous land link between the remote East Malaysian states of Sarawak and Sabah. Running 335 kilometres through Limbang, Lawas and the northern Sarawak interior, it is intended to give more than 70,000 residents of underserved communities year-round access to schools, hospitals and jobs, and to open a region with significant agricultural and tourism potential. The need for a year-round connector became acute during the pandemic, when international border closures cut these communities off overnight.

Delivery is led by Jabatan Kerja Raya Sarawak (JKRS), the state public works department, on a federally approved budget of MYR 7.15 billion. Construction started in June 2024 against a 60-month programme, with completion expected in June 2029.

Why a digital-first approach

The corridor crosses mountainous terrain with widely varying soil conditions and some of the heaviest rainfall in Malaysia. Teams work across hard-to-reach sites, alongside protected areas and timber concessions, and under frequent design changes and community scrutiny. With only 60 months to deliver, JKRS moved off traditional 2D drawing workflows and basic file sharing onto an integrated 3D and 4D digital twin environment.

The deployment

  • Common data environment — ProjectWise connects design consultants, contractors and government agencies in one traceable repository, tightening document control and shortening design reviews across project zones.
  • 3D corridor design — OpenRoads Designer handles geometric alignment, corridor modelling, terrain analysis, drainage design and slope stabilisation planning, letting engineers optimise layouts against geotechnical conditions in real time.
  • Geospatial coordination — OpenCities Map layers engineering models over cadastral, utility and environmental datasets, so land acquisition, timber concession boundaries and environmental buffers are resolved with land offices, forestry departments and utility providers before they become site problems.
  • 4D construction sequencing — SYNCHRO 4D simulates construction sequences and logistics against real-world site constraints, exposing clashes and informing manpower and plant planning.
  • Reality capture — iTwin Capture turns monthly drone surveys into photorealistic 3D reality models of each work front.
  • Web-based 3D viewing — Cesium publishes those models to a browser-based 3D visualisation platform, so stakeholders who cannot reach the sites can inspect progress themselves.

Outcomes

Working inside the integrated digital twin platform accelerated the design process by 50% and cut overall project costs by 30%. Coordinating engineering data against environmental and land datasets reduced the impact on protected areas and wildlife by 80%, and the project's carbon footprint fell by 30%. JKRS also reports shorter design cycles, more accurate construction plans and stronger stakeholder engagement, and is exploring carrying the twin forward into the operational phase to manage the completed road through its lifecycle.

Recognition

SSLR2 won the Roads and Highways category of the 2025 Going Digital Awards at Bentley Systems' Year in Infrastructure event in Amsterdam in October 2025, chosen from close to 250 entries submitted from 47 countries. JKRS Director Cassidy Anak Morris, quoted below, presented the project to the independent judging panel and framed the result as a benchmark for infrastructure delivery across Malaysia.

Quotes

With Bentley software technology, we systematically collect, analyze, and manage data throughout the project lifecycle. Asset performance can be optimized, maintenance costs reduced, and public safety enhanced. Apart from maximizing the return on investment, we ensure sustainable infrastructure for generations to come by transforming roadway construction through digital twin excellence.

We are proud to introduce innovative digital approaches used in the delivery of sustainable infrastructure projects. For the SSLR2 project, the hilly terrain in the north of Sarawak requires a sustainable engineering and project management approach.

Project Summary

This information is available to registered members of XRHQ. Sign up for free below.

Experience

Available to XRHQ members

Software

Available to XRHQ members

Funding & Commercials

Available to XRHQ members

Sources

Available to XRHQ members

Know more about this project? Help us fill in any missing details.

Edit this project →

SUBMITTED BY

Dave

Were you involved in this project?

This write-up is free to reuse with credit — CC BY 4.0.